West Campus Roads (Increment II)
Project: West Campus Roads (Increment II)
General Use: Roadways and Parking
Lineal Yards: TBD
Status: Design
- Entry Road Area #2A: COMPLETE
Engineer: Associated Engineering Group
Budgeted Cost:
- Parking Area #1: $3,860,000
- Entry Road Area #2A: $92,361.38 (Final Cost)
- Loop Road Area #3: $1,450,000
- Loop Road Area #4: $1,056,000
- Loop Road Area #5: $2,970,000
- Brink Entry Area #6: $1,390,000
Construction Start: Area #3-6: Spring 2016; Parking Area #1: Spring 2017
Opening (anticipated): Area #3-4: Summer 2016; Area #5-6: Fall 2016; Parking Area #1: Winter 2017
Project Goal
This project will provide upgrades to the existing roads and includes new parking
areas, bus turnouts and bike lanes.
Project Status Updates
Current Bulletin: 10/22/2018
Previous Bulletin: 10/15/2018
Earlier updates have been archived. Please contact the webmaster for access.