Parking Structure/Lot - East Campus

MJC Parking Lot schematicProject: Parking Structure/Lot

General Use: 455 total parking spaces in lot (net gain of 246 spaces)

Square Feet: N/A

Status: COMPLETE

Engineer: Associated Engineering, Inc.

Final Cost: $3,828,529

Construction Start: February 2009

Opening: August 2009

Project Goal

Provide additional parking at the East Campus in the most cost effective manner.

Update: February 8, 2008

YCCD purchased a 3.75 acre parcel of land on the west side of Tully Road for the expansion of a parking on Modesto Junior College's East Campus. The parcel is adjacent to land already owned by the district, part of which is currently developed as a 200-space parking lot. The new land allowed the district to add 237 parking spaces, bringing the lot total up to 455 spaces.

​Project Status Updates

There are currently no bulletins to view.

Earlier updates have been archived. Please contact the webmaster for access.

​Links of Interest

MJC Parking Study DRAFT, September 2005

MJC Parking Study, January 2006

MJC Parking Study Attachments A-F

MJC Parking Lot Presentation, August 2008

MJC Parking Lot Presentation, June 2009