Skip to page content

Pinyon Building Upgrade

Pinyon BuildingProject: Pinyon Building Upgrade

General Use: General Instruction

Square Feet: 1,440

Status: Bid Award

Architect: Lionakis

Budgeted Cost: $257,345

Construction Start: September 2016

Opening: March 2017

Project Goal

Renovate the space for Student Health Services/Nurse

Overview

Create shared conference room with 1-2 exam rooms with adjustments to the interior walls and ceilings. Upgrade the existing unisex restroom with minor adjustments to the existing restrooms for new spaces. New finishes on the walls and floors will be included.

Project Status Updates

Current Bulletin: 05/01/2017

Previous Bulletin: 04/24/2017

Earlier updates have been archived. Please contact the webmaster for access.